Couldwell Concrete - 50th Anniversary Banner

North Durham Academy

This project is for a brand new Academy campus which will open to students in 2013. This visionary project will create an inspiring, flexible learning environment for students and provide superb facilities for the local community. The campus will derive its distinctive identity from the world of work, with state of the art teaching and learning areas.

Client: Hall Construction Services Ltd
Project: North Durham Academy
Location: Stanley – Co. Durham
Project duration: Overall sub-contract programme: 10 weeks
Project completion date: June 2012
Sub-contract value:  450K

Services provided:

  • 5,000m2 Internal Ground Floor Slabs – 300/350mm thick with 2 layers of mesh reinforcement. Traditional hand-laid floors with a powerfloated finish to class SR3 in accordance with BS 8204-2: 2003
  • 9,000m2 Upper Floors – Composite metal deck 150mm thick with 1 layer of continuous mesh reinforcement. Pumped concrete with a powerfloated finish to class SR3 in accordance with BS 8204-2: 2003

Why we were chosen:

  • Vast experience & expertise in all types of in-situ concrete floors
  • CCF Ltd able to handle a ‘multi-floor’ sub-contract package with full supply of materals.