Couldwell Concrete - 50th Anniversary Banner

Specialist Application – Dry Shake Topping

4th March 2015 dry shake topping

Dry Shake Topping is the kind of specialist job we don’t get to do everyday!

This project was a repeat business order from a very valued client – Hall Construction Services Ltd.

[hr]

Client: Hall Construction Services Ltd
Project: Hydram Engineering
Location: Chilton, Co Durham
Project duration: 2 days; one preparation day and one pour day
Project completion date: 16th February 2015
[hr]

Services provided:

  • Sikafloor SynTop-2 Dry Shake Topping (Coloured) – Tile Red.
  • 1000m2 Machine laid using laser controlled levelling to FM3 powerfloat finish.
  • 200mm thick Ground floor slab with one layer of A252 mesh with saw-cut joints.

Why we were chosen:

  • As preferred sub-contractor for the works together with our relationship and quality of workmanship we provide.