Couldwell Concrete - 50th Anniversary Banner

Distribution Facility, Sheffield – UC Build Ltd

3rd October 2023 uncategorized

Our Client: UC Build Ltd

Project: Distribution Facility

Location: Sheffield

Project Duration: 10 Days

Project Completion: March 2023

Sub-Contract Value: £500k

 

Services Provided:

  • Bespoke Design, and full supply of labour, plant & materials
  • 180mm thick ground floor slab with one layer of A193 mesh and saw cut joints
  • 12,000m2 machine laid using laser-controlled levelling to FM2 Classification, in line with TR34 4th edition
  • Independent floor level survey to verify FM2 Classification

 

Why we were chosen:

Bespoke Design Service, and experience in laying FM1 & FM2 classification floors